Blacktopping starts on Karnali corridor, 130 km contracted

Post Thumbnail

KATHMANDU: Blacktopping work has started on the Karnali Corridor, a major strategic road in Karnali Province. The first phase covers a 6-km section from Pilichaur towards Dhulachaur in Bajura district.

The work is part of the 123-km southern section of the corridor, which runs from Khulalu to Sallisalla. This is the first time blacktopping has started on the Karnali Corridor.

According to Infrastructure Development Minister Sunil Lamsal, a total of 23 km will be black-topped under the current package within the next two years.

The government has also awarded contracts for another 41 km of the southern section. These include the Khulalu-Kot, Bhukka Khola-Pilichaur and Tumcha-Sallisalla stretches.

Yeti Builders Pvt Ltd has secured the contract for the 13-km Khulalu-Kot section in Kalikot for Rs 753.13 million, excluding VAT.

Similarly, Lama-Sunkoshi JV has received the contract for the 15-km Bhukka Khola-Pilichaur section for Rs 704.66 million. Pacific Engineering Company has secured the contract for the 13-km Tumcha-Sallisalla section in Humla for Rs 724.72 million.

Earlier, contracts had been awarded for blacktopping 50 km of the southern section. These include the 23.7-km Pilichaur-Kuwadi stretch and the 27.3-km Kuwadi-Tumcha stretch.

PS Construction received the contract for Pilichaur-Kuwadi for Rs 977.8 million, while Conteck-Singh JV secured the Kuwadi-Tumcha contract for Rs 1.049 billion. Construction work is underway on both sections.

The government has also awarded contracts for 39 km of the northern section. Divyajyoti Construction has received the contract for the 18.2-km Kharpunath-Kharikhet section in Humla for Rs 856.21 million, including VAT and provisional sums.

The contract for the 20.8-km Kharikhet-Sallisalla section has been awarded to SKCPL/BNT/Bagmati Joint Venture for Rs 1.007 billion.

The newly contracted sections are targeted for completion within three years.

The 269-km Karnali Corridor connects Khulalu in Kalikot with the Hilsa border point with China. Contracts have now been awarded for blacktopping a total of 130 km of the corridor.

Last year, the Ministry of Finance approved a budget source guarantee of Rs 6.11 billion for upgrading both the northern and southern sections.

The Karnali Corridor is a strategic road connecting Nepal with India and China. It links the Jamunaha border point in Banke with Surkhet, Kalikot, Bajura and Humla before reaching Hilsa on the Chinese border.

The road is considered a lifeline for Karnali Province. Its upgrade to a two-lane road is expected to improve connectivity, make daily travel easier, support tourism and facilitate cross-border trade.

Blacktopping starts on Karnali corridor, 130 km contracted

Motorcycle, scooter imports up 26.4% in first quarter

Previous article
Blacktopping starts on Karnali corridor, 130 km contracted

Fixed vs floating rate: which makes your auto…

Next article