KATHMANDU: The Dhulikhel-Dapcha section of the BP Highway is set to be upgraded into a two-lane road, with the Initial Environmental Examination (IEE) report nearing completion.
The 20.6-km section, stretching from Dhulikhel in Kavrepalanchok to Dapcha (Bridge No. 1) in Namobuddha, will be widened from its existing 5.5 meters to 10 meters.
According to the Bhaktapur Road Division Office, the Detailed Project Report (DPR) has already been completed. The project is estimated to cost Rs 3.7978 billion, averaging around Rs 180.5 million per kilometer.
Suman Yogesh, chief of the Bhaktapur Road Division Office, said the IEE report is in its final stage. The office has also submitted a proposal to the Ministry of Infrastructure Development to secure the required budget.
The tendering process will begin once funding is secured.
During the expansion, retaining walls will be built in suitable locations, while hillsides will be cut in difficult sections to widen the road. The project passes through four municipalities: Dhulikhel, Panchkhal, Panauti and Namobuddha.
Yogesh said compensation has already been distributed for land and structures located within 15 meters on either side of the road. Some trees will need to be cut, and a few houses may have to be demolished to improve curves, particularly between Dhulikhel and Bhandarbesi.
The project is targeted for completion within three years of the contract agreement.
Meanwhile, the 30.5-km Bhandarbesi-Nepalthok section of the BP Highway is also being reconstructed as a two-lane road. The section was damaged by floods in September and October 2024 and 2025 and is being rebuilt under five separate contract packages.
Of the total section, the Nepal government is rebuilding 27.3 km, while the Japan International Cooperation Agency (JICA) is handling the remaining 3.2 km. Four contract packages are in Kavre and one is in Sindhuli.
Once the Dhulikhel-Nepalthok sections are upgraded, travel from Kathmandu towards eastern Nepal is expected to become faster and easier. The road is being designed for a vehicle speed of up to 60 kmph. From Nepalthok, travelers will also be able to reach Khurkot through the Mid-Hill Highway.
Building a two-lane road along the existing BP Highway between Nepalthok and Khurkot is geographically difficult. Therefore, a contract has already been awarded to construct a two-lane bridge over the Sunkoshi River at Nepalthok.
The BP Highway is the shortest road connecting Kathmandu with the Mid-Hill region and eastern Nepal. More than 5,000 vehicles travel along the highway every day.
Construction of the 160-km Dhulikhel-Sindhuli-Bardibas highway began in fiscal year 1996/97 with grant assistance from the Japanese government. Japan formally handed over the completed highway to the Nepal government on July 2, 2015.