KATHMANDU: The Mahadevtar Tunnel, the longest tunnel on the Kathmandu-Terai/Madhesh Fast Track, has achieved a breakthrough, marking another milestone in the construction of the national pride project.
The 3,445-metre right-hand tunnel, which will carry traffic from Nijgadh towards Kathmandu, achieved a breakthrough on Wednesday morning (November 18, 2026). President Ramchandra Paudel attended the breakthrough ceremony.
Earlier, the 3,486-metre left-hand tunnel, which will carry traffic from Kathmandu towards Nijgadh, achieved a breakthrough on September 3, 2026.
Seven tunnels with a combined length of 11.21 km are being constructed along the Fast Track, with separate tunnels for traffic in each direction. Both tunnels at Mahadevtar, along with those at Dhedre and Lendanda, have now achieved breakthroughs.
Secondary lining work has also been completed in the 1,622-metre Lendanda tunnel and the 1,690-metre Dhedre tunnel.
Lining work is progressing alongside excavation at Mahadevtar. More than half of the lining work has been completed in the left-hand tunnel, while over one-third has been completed in the right-hand tunnel. China State Construction Engineering Corporation is constructing the Mahadevtar tunnel package at a cost of Rs 21.61 billion.
Meanwhile, excavation is progressing at other tunnel sections. Of the 2,250-meter Chandram Bhir tunnel, 847.7 meters have been excavated. Similarly, 153.6 meters of the 1,087-metre Daibichaur tunnel and 64.4 meters of the 520-metre Sisautar tunnel have been completed. Preparatory work for the portal of the 583-metre Mauribhir tunnel is underway.
Construction of the Fast Track began in 2017. As of the end of Ashoj 2083 (October 17, 2026), overall physical progress had reached around 51 percent. The project had spent Rs 95.17 billion, including mobilization advances.
The estimated total project cost stands at Rs 211.93 billion, making it one of Nepal’s largest ongoing infrastructure projects in terms of budget.
After failing to meet its previous deadlines, the government has extended the project deadline for a third time. A Cabinet meeting held on August 5, 2026, approved a three-year extension, setting the new completion deadline for April 13, 2030.