KATHMANDU: Contracts have been awarded to blacktop an additional 80 km section of the Karnali Corridor, a strategic road connecting Nepal with the Chinese border. The project is targeted for completion within three years.
The Karnali Corridor Project has selected contractors to upgrade the 80 km road section, divided into five packages. The total contract value is Rs 4.03 billion.
The 269 km Karnali Corridor connects Khulalu in Kalikot with Hilsa on the Nepal-China border. The road is being developed in two sections: the 123 km southern section from Khulalu to Salisalla and the 146 km northern section from Simikot to Hilsa.
Under the latest contracts, 41 km of the southern section will be upgraded through three packages, while 39 km of the northern section will be upgraded through two packages.
In the southern section, the 13 km Khulalu-Kot package has been awarded to Yeti Builders Pvt. Ltd., Satdobato, for Rs 753.13 million, excluding VAT.
Similarly, Lama-Sunkoshi JV has secured the contract for the 15 km Bhukka Khola-Piluchaur section for Rs 704.66 million. Pacific Engineering Company has been awarded the 13 km Tumcha-Salisalla package in Humla for Rs 724.72 million.
Infrastructure Development Minister Sunil Lamsal said a multi-year program worth more than Rs 3 billion had been approved for upgrading the southern section. He said construction would now move forward after delays caused by budget shortages.
In the northern section, Divyajyoti Construction has secured the contract for the 18.2 km Kharpunath-Kharikhet section for Rs 856.21 million, including VAT and provisional sums.
The 20.8 km Kharikhet-Salisalla section has been awarded to SKCPL/BNT/Bagmati Joint Venture for Rs 1.00 billion.
With the latest contracts, a total of 130 km of the Karnali Corridor will be under blacktopping contracts. Earlier, contracts had been awarded for two sections covering 50 km in the southern corridor.
PS Construction was awarded the 23.7 km Piluchaur-Kuwadi section for Rs 977.8 million. The 27.3 km Kuwadi-Tumcha section was awarded to Contekar Singh JV for Rs 1.049 billion. Construction is currently underway on both sections.
Bel Bahadur Nepali, acting project chief of the northern section, said contractors had been selected to upgrade the 39 km road from Kharpunath to Salisalla. Agreements will be signed with the selected companies soon to begin construction.
Meanwhile, the proposed expansion of around 95 km of road between Simikot and Hilsa into a two-lane highway by the Chinese government remains uncertain.
A Chinese team conducted a feasibility study in June 2025 but has not contacted the Nepalese side since then, according to Nepali. The government is now considering preparing a Detailed Project Report (DPR) and moving ahead with the work on its own.
The Ministry of Finance had secured funding of Rs 6.11 billion last year for upgrading both the northern and southern sections of the Karnali Corridor.
The Karnali Corridor is a strategic road linking Nepal, India and China. It starts at the Jamunaha border point in Banke, passes through Surkhet, Kalikot, Bajura and Humla, and reaches Hilsa on the Chinese border.
Once upgraded to a two-lane road, the corridor is expected to improve connectivity in Karnali Province, support tourism and facilitate cross-border trade. It is also considered vital for the daily lives of people living in the region.