Fast track construction accelerates as 13 bridges are completed

KATHMANDU: Construction of the Kathmandu-Tarai/Madhesh Fast Track has picked up speed in recent months. The national pride project had seen slow progress for several years. The project started in 2017 with a six-year completion target. Average annual progress stayed near…
News

Nepal Army making progress on four North–South strategic roads

KATHMANDU:  Along with national security, the Nepal Army has been active in development work, especially in road construction across difficult terrain. The government has continued assigning the Army to build road sections that the Department of Roads has not been…
News

Fast-Track work advances on 12 packages, progress hits 64%

KATHMANDU: The Kathmandu-Terai/Madhesh Expressway, one of Nepal’s National Pride Projects, has achieved an overall physical progress of 43.66 percent. Initiated in 2017 with a six-year completion target, the project has completed less than half of the total work in eight…